Custom Development Software Process
Navigation: Testing> Monitoring and Controlling

Pre-Condition:

- Completed Assembly Testing

 

Activities:

Task Name PIC Template Standard/Procedure Guideline/Process
Perform Risk Analysis Project Manager      
Evaluate, Confirm Resources Project Manager, Resources Manager      
Update Project Schedule Project Manager      
Update EFM with Exception Memo (if needed) Project Manager EFM Template    
Create Project Status Report (for Steering Committee) Project Manager Project Status Report Template    
Discussion (backed by Minutes of Meeting) Project Manager Project Meeting Minutes Template    

 

Post-Condition:

- Risks are analyzed
- Project's Resources is evaluated
- Requested resources is confirmed
- Project schedule is updated
- EFM is updated
- Internal status report is created and submitted every two weeks
- Update to steering committee is done