Custom Development Software Process
Navigation: Production> Release

Pre-Condition:

- Completed Production Testing

 

Activities:

Task Name PIC Template Standard/Procedure Standard/Procedure
Create "Final" tag in SVN to freeze documents and source code Technical Lead     SVN Practice User Guide
Update Project Generation Document Technical Lead Project Generation Template    
Update the Version Control document Technical Lead Version Control template    

 

Post-Condition:

- Backup
- Final Custom
- Project Backup
- Production is signed off